Deconone is one company to join this project to demolition the Queen Sirikit National Convention center.
Project summary
Demolition of the entire building including foundation.
Schedule of work
- Install protective fences.
- Dismantling internal architecture work, escalators, elevators and water and electricity systems
- Demolition building from ceiling to foundation.
- Leveling the ground level
Approx. value
60 million Baht
Area
280,000 ตร.ม.
Services
Demolition entire building
Duration
8 months
Location
Klong Toey
Status
Completed